Construction on the new roundabout in East Wenatchee at 3rd St. SE and Highline Drive between Costco and a couple of car dealerships, Apple Valley Honda and Town Toyota, begins Thursday, April 23rd with the intersection completely closed to traffic for three weeks beginning Monday, April 27th with a couple of additional days of being closed near the end of the project.

Work is expected to be completed by June 19th.

The city also says work on the Complete Streets project will start on Monday at three different locations with closures and detours.

The city has posted a website with updates, maps with detours and more on their website.